In 1938 a major flood
protection scheme was carried out at Bures with an automatic lock
built on the original lock site
When the Automatic Weir was installed
little thought was given to the fish population along the river
as it blocked their path to swim downstream.
Now that fishing along the River Stour has become very popular,
the
fishermen downstream are obviously at a disadvantage compared to
those upstream.
|
|
The 1920
map opposite clearly shows the river course with two distinct feeds
into the Mill Pond.
The lower channel was necessary if both the Lock and the Mill Sluices
were shut, providing a diversionary overflow path.
Bottom left of picture >>>>>>>>>>> |
|
The EA is in the process of constructing
a "Fish Ladder" which will allow fish to swim downstream
using a dried up channel which has not been in use, possibly since
the 1930`s
In recent years, a dramatic increase
in leisure craft such as canoes have been using the river. Now the
Weir was not only an obstacle to the fish stock, but canoeists have
to "portage" from the "Cambridge Brook" inlet,
past the Weir and eventually back into the river at the Mill Pond.
|
A very strenuous task indeed.
However, it soon became apparent that Canoeists could also benefit
from this work.
If the existing concrete bridge was raised it would allow safe passage
for the canoes using the ditch without the need to raise them out
of the water.
The EA agreed to this proposal instigated by "River Stour
Boating" and a new raised "Oak Footbridge" was
constructed which will allow sufficient height for canoes to pass
underneath.
The completed task will finally look
like this.
The Yellow footbridge is the existing path with a new solid oak
bridge shown in red leading
onto the meadow on the southern side of the river
Click on the images below to enlarge
|
|
Channel yet to be filled with water
looking towards Mill Pond
|
The Channel will only be filled with
approx. 12" of water,
this image does give some indication of its depth.
|
Footbridge
|
New extension to Footbridge, looking
towards the Colchester Rd.
|
|
Footbridge with the Weir in the background
|
July 2009 - Channel dry
|
|
February 2010 - Channel now in flood
|
Fish Ladder and Entrance to Channel
|
|
<<
In flood, January 2014 |